7th April 2026 MAJOR Update
It's time to tell the world.
Last week a contract was signed with Romaldi Constructions to build our new community facility in Park 21W. We have already met with them onsite and visible activity will start this week.
This is a significant milestone for the project and a massive milestone for your Club.
A media release is being released today, and we have also started contacting, acknowledging, and thanking a multitude of people and organisations who have been part of the journey, all of whom played a role in getting us to where we are now.
We expect the first building to be completed around September. The existing facility will then be demolished and the second built through next summer/autumn.
We will soon share a lot more detail about the construction phase, including the way we co-exist with Romaldi, but for now let's celebrate this massive achievement!
February 2026 Update
We're getting very close!
Community Facility
While it was hard to make significant progress over Xmas/New Year, the last few weeks has seen a lot of fine tuning in the final design tweaks and cost management between us, Council, and the project management team.
Although aspects of the tender process remain confidential, we are still on track for construction to commence this quarter. If this timeline is met, then we would expect the first building to be completed at the end of the winter season. The existing facility will then be demolished and the second built through next summer/autumn.
All of our members who have been part of or following this journey for over 8 years will understand that targeted timelines aren't always achieved (!!!), but the good news now is that we are now discussing these timelines in months not years which is sensational.
Don't be concerned if there is some silence for several weeks as an official public announcement cannot be made until all legal and probity steps are complete, including dotting i's and crossing t's on a contract. Once this is done, we can tell the world as well as start to plan an event to celebrate!
Playing Fields
As reported late last year, we are also progressing the planning and design of playing field re-alignment and irrigation. The details around this will start to become clearer over the next couple months and will be shared as soon as possible. The two biggest issues for this part of our overall master plan are the cost to replace irrigation and re-align fields, and how to minimise disruption to all of our users (ALSC, ACSARA, many others) as work is performed. Both of these challenges mean that the project will likely be done in stages, with priority given to the main field that will be immediately adjacent to the new community facility.
Mid-November 2025 Update
After a somewhat frustrating process of detailed design, the Park 21W project went out to tender in early November and bids from approximately 4 builders are due early December. We are hoping that the price comes in at a reasonable level, however if we get bids that exceed the existing available funding, there will need to be a small period of 'value management' in an effort to lower the cost.
December will be yet another pivotal period for our project. The most likely timeline if costs are ok, is for a contract to be signed in January and construction commencing Feb/Mar.
Council approval bureaucracy is slow at the best of times and even worse over Xmas /New year, but at least we continue to head in the right direction.
In parallel to the construction of the facility next year, we have progressed planning for the field re-alignment and improvement. A preliminary report has been received from an independent expert over the remainder of 2025 we will look to better understand the likely cost, nature and staging of works to improve irrigation, extend, re-align and in some areas re-develop the fields.
Mid-July 2025 Update
Mid-June 2025 Update
21st April 2025 Update

24th March 2025 Update
Things have really escalated over the last 6 weeks, with formal Steering Committee meetings with Council Administration occurring almost weekly.
9th February 2025 Update
Following approval of the single-story concept design in December for our new Park 21W facility, we have been liaising with Council to progress with detailed design and a range of other aspects to get the project underway with momentum.
It's difficult to make progress over the Xmas/NY period, however since mid-January we have:
10th December 2024 Update

At tonight's Council meeting Council our preferred single-story concept design option for the new facility at our home in Park 21W was approved.
As outlined below there are still challenges and risks but the big rock has been cracked.
The image above shows the vote with the Chamber in favour 7:1.
A massive milestone has been reached.
3rd December 2024 Update
At the 3rd December Committee meeting the Council endorsed the following:
There remain future challenges as we work hard in 2025 to progress detailed design, secure a long-term lease, tender for a builder and commence construction. Before any of this can occur though, the Council need to formally adopt the endorsements from last night's Committee meeting at the full Council meeting on December 10th. Watch this space.
Early December 2024 Update
Mid-October 2024 Update
The last 12-18 months has seen painfully slow progress, but we are at least now at the following juncture:
We have been disappointed many times before by Council timelines extending way beyond reasonable limits but are pushing for the above to be approved this calendar year. If this occurs it will be the catalyst for tangible action and progress, not just for Park21W but for all lovers of community sport and recreation in the parklands.
Background and recap since 2017!
The redevelopment of Park21W is a long time in the making.
In 2016/17 we won an Expression of Interest to partner with Council to improve the area. A master plan was approved comprising a new sports facility to cater for the growing number of codes, genders and age groups playing at Park 21W, re-aligning, irrigating and expanding the lighting of the playing fields, new cricket training nets and pitches, and associated landscaping, footpaths and public toilets.
Since then, we have planned and progressed many aspects, invested significant amounts of club money, raised significant sums from sponsors and donors, spent thousands of volunteer hours, and faced numerous hurdles along the way - initially with funding, then COVID interruptions, and more recently with obtaining Council support for the design of the facility.
There have been some wins:
Sporting Facility
The new sporting facility will comprise multiple change rooms, safe and protected viewing, a community space and significantly more storage space. It will be a facility that supports the operations of our club, as well as the broader ACSARA membership. The general public, as well as other community groups, clubs and schools will be encouraged to also use the facility.
There are many aspects and stages to work through in a project like this. The three primary ones in our case are:
